LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Red River County

Tap 138kV Rivercrest SES 1780 - Deport REA 1768

2 active projects totalling 255 MW are queued to connect at Tap 138kV Rivercrest SES 1780 - Deport REA 1768 in Red River County, Texas, according to ERCOT's October 2026 report.

Active capacity
255 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0124Silverbell StorageBESS129FIS Requested09/30/20280
28INR0125Silverbell SolarSolar126FIS Requested09/30/20280