Woodfin Switch (#1465) 345kV
1 active project totalling 352 MW is queued to connect at Woodfin Switch (#1465) 345kV in Lamar County, Texas, according to ERCOT's October 2026 report.
Active capacity
352 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0186 | Rowdy Creek Solar | Solar | 352 | IA Signed | 12/29/2027 | 0 |