LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Lamar County

Pacific Switch (PACSW) 345 kV Bus 11683

1 active project totalling 287 MW is queued to connect at Pacific Switch (PACSW) 345 kV Bus 11683 in Lamar County, Texas, according to ERCOT's October 2026 report.

Active capacity
287 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0409Baker Branch BESSBESS287FIS Requested12/31/20290