1 active project totalling 1,232 MW is queued to connect at 1692 Paris Switch 345kV in Lamar County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,232 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
30INR0002Southeast Oklahoma Pumped StorageOther1,232FIS Requested01/01/20300