LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Kleberg County

5646 Riviera Substation 69kV

1 active project totalling 75 MW is queued to connect at 5646 Riviera Substation 69kV in Kleberg County, Texas, according to ERCOT's October 2026 report.

Active capacity
75 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0516French Riviera StorageBESS75FIS Requested05/01/20280