LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Kenedy County

Tap 345kV 80076 Ajo 80076 - 8601 Cebolla

1 active project totalling 178 MW is queued to connect at Tap 345kV 80076 Ajo 80076 - 8601 Cebolla in Kenedy County, Texas, according to ERCOT's October 2026 report.

Active capacity
178 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0189Green Ocelot StorageBESS178FIS Approved11/17/20280