The Kenedy Switching Station #2 (#8186) to Rosata POD (#8153) Line ; AEP

1 active project totalling 157 MW is queued to connect at The Kenedy Switching Station #2 (#8186) to Rosata POD (#8153) Line ; AEP in Karnes County, Texas, according to ERCOT's October 2026 report.

Active capacity
157 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0151Coyote Den StorageBESS157FIS Requested09/30/20300