Substation / point of interconnection ยท Jefferson County
40850 Jordan
1 active project totalling 1,298 MW is queued to connect at 40850 Jordan in Jefferson County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,298 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0020 | Willow Oak Gas | Gas | 1,298 | FIS Requested | 01/01/2030 | 0 |