Substation / point of interconnection ยท Jack County
1506 Long Hollow Switch 345 kV
1 active project totalling 306 MW is queued to connect at 1506 Long Hollow Switch 345 kV in Jack County, Texas, according to ERCOT's October 2026 report.
Active capacity
306 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0657 | O'Bannion Energy Storage | BESS | 306 | IA Signed | 04/21/2028 | 0 |