Substation / point of interconnection ยท Hopkins County
138 kV Ridgeway Switch
1 active project totalling 82 MW is queued to connect at 138 kV Ridgeway Switch in Hopkins County, Texas, according to ERCOT's October 2026 report.
Active capacity
82 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0326 | Blarney Solar | Solar | 82 | IA Signed | 10/01/2027 | 0 |