1 active project totalling 154 MW is queued to connect at 7180 L_ZORN__8_1Y 138kV in Guadalupe County, Texas, according to ERCOT's October 2026 report.

Active capacity
154 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0117Roble BESSBESS154FIS Requested12/01/20280