Substation / point of interconnection ยท Guadalupe County
345kV 7042 Zorn Substation
5 active projects totalling 2,000 MW are queued to connect at 345kV 7042 Zorn Substation in Guadalupe County, Texas, according to ERCOT's October 2026 report.
Active capacity
2,000 MW
queued at this substation
Active projects
5
5 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0532 | Alpha Power Phase 1 | Gas | 400 | FIS Requested | 12/31/2028 | 0 |
| 29INR0363 | Alpha Power Phase 2 | Gas | 400 | FIS Requested | 12/31/2029 | 0 |
| 30INR0143 | Alpha Power Phase 3 | Gas | 400 | FIS Requested | 12/31/2030 | 0 |
| 31INR0025 | Alpha Power Phase 4 | Gas | 400 | FIS Requested | 12/31/2031 | 0 |
| 32INR0007 | Alpha Power Phase 5 | Gas | 400 | FIS Requested | 12/31/2032 | 0 |