ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Grayson County

Tap 138 kV Haggerty Switch (12677) to Van Al (1754) 138kV

1 active project totalling 101 MW is queued to connect at Tap 138 kV Haggerty Switch (12677) to Van Al (1754) 138kV in Grayson County, Texas, according to ERCOT's October 2026 report.

Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0234Lima Solar ProjectSolar101IA Signed03/01/20290