Substation / point of interconnection ยท Galveston County
Bus Name: TNHEIGHTS_1
1 active project totalling 205 MW is queued to connect at Bus Name: TNHEIGHTS_1 in Galveston County, Texas, according to ERCOT's October 2026 report.
Active capacity
205 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0340 | SOUTHERN SELECT ENERGY STORAGE | BESS | 205 | IA Signed | 05/24/2027 | 0 |