LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Galveston County

42000 P. H. Robinson 345kV

1 active project totalling 1,029 MW is queued to connect at 42000 P. H. Robinson 345kV in Galveston County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,029 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
30INR0003Hecate Energy Jamaica WindWind1,029FIS Requested06/01/20300