Tap 138kV 3279 Long Lake Tap Switch - 3280 Long Lake
1 active project totalling 86 MW is queued to connect at Tap 138kV 3279 Long Lake Tap Switch - 3280 Long Lake in Freestone County, Texas, according to ERCOT's October 2026 report.
Active capacity
86 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0289 | Ratcliff Solar | Solar | 86 | FIS Requested | 04/07/2029 | 0 |