Substation / point of interconnection ยท Ellis County
1940 Midlothian ELP 345kV
1 active project totalling 18 MW is queued to connect at 1940 Midlothian ELP 345kV in Ellis County, Texas, according to ERCOT's October 2026 report.
Active capacity
18 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0543 | Midlothian Unit 3 repower | Gas | 18 | FIS Requested | 06/03/2028 | 1 |