Substation / point of interconnection ยท Duval County
Tap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1
2 active projects totalling 402 MW are queued to connect at Tap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1 in Duval County, Texas, according to ERCOT's October 2026 report.
Active capacity
402 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0124 | Apricot Sun Solar | Solar | 201 | FIS Requested | 09/30/2029 | 0 |
| 29INR0125 | Apricot Sun Storage | BESS | 201 | FIS Requested | 09/30/2029 | 0 |