ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection · Duval County

Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP

0 active projects totalling 0 MW are queued to connect at Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP in Duval County, Texas, according to ERCOT's October 2026 report.

Active capacity
0 MW
queued at this substation
Active projects
0
2 projects ever listed
Withdrawn share EST
100%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0196Realitos Solar SLFSolar150Withdrawn12/15/20280
26INR0195Realitos Storage SLFBESS0Withdrawn12/15/20280