ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Duval County

138 kV Zenaida Bus# 80043

2 active projects totalling 248 MW are queued to connect at 138 kV Zenaida Bus# 80043 in Duval County, Texas, according to ERCOT's October 2026 report.

Active capacity
248 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0391Jumping Cactus StorageBESS125FIS Requested09/30/20290
26INR0393Dove Wing StorageBESS122FIS Requested09/30/20290