1 active project totalling 150 MW is queued to connect at (#78575) LCRA Yorktown 138 kV in Dewitt County, Texas, according to ERCOT's October 2026 report.
Active capacity
150 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0328 | Yorktown BESS | BESS | 150 | FIS Requested | 12/16/2028 | 0 |