River Oaks (7173)

1 active project totalling 200 MW is queued to connect at River Oaks (7173) in Comal County, Texas, according to ERCOT's October 2026 report.

Active capacity
200 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
28INR0436Englehardt BESSBESS200FIS Requested09/01/20270