Substation / point of interconnection ยท Cameron County
5764 East Rio Hondo Substation 138kV
1 active project totalling 201 MW is queued to connect at 5764 East Rio Hondo Substation 138kV in Cameron County, Texas, according to ERCOT's October 2026 report.
Active capacity
201 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0385 | Bobcat Cameron BESS | BESS | 201 | FIS Requested | 12/31/2027 | 0 |