LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Burnet County

7065 DOBVI 138kV

1 active project totalling 104 MW is queued to connect at 7065 DOBVI 138kV in Burnet County, Texas, according to ERCOT's October 2026 report.

Active capacity
104 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0499Mineral Springs BESSBESS104FIS Requested11/02/20270