Substation / point of interconnection ยท Brown County
1444 Brown Switch - 3348 Russell Gap 345 kV Line
1 active project totalling 256 MW is queued to connect at 1444 Brown Switch - 3348 Russell Gap 345 kV Line in Brown County, Texas, according to ERCOT's October 2026 report.
Active capacity
256 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0291 | Nouveau BESS | BESS | 256 | FIS Requested | 12/15/2027 | 0 |