Substation / point of interconnection ยท Brooks County
80078 Reforzar Switch Station 345kV
1 active project totalling 261 MW is queued to connect at 80078 Reforzar Switch Station 345kV in Brooks County, Texas, according to ERCOT's October 2026 report.
Active capacity
261 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0059 | Verily Solar (FKA Cuello De Cuero Solar) | Solar | 261 | FIS Requested | 07/01/2029 | 0 |