LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Bell County

3687 Bell County East 345kV

1 active project totalling 352 MW is queued to connect at 3687 Bell County East 345kV in Bell County, Texas, according to ERCOT's October 2026 report.

Active capacity
352 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0070Chillingham SolarSolar352Sync Approved10/31/20260