Substation / point of interconnection ยท Austin County
7287 Bellville North 138kV
1 active project totalling 251 MW is queued to connect at 7287 Bellville North 138kV in Austin County, Texas, according to ERCOT's October 2026 report.
Active capacity
251 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0252 | Parula Energy Center | BESS | 251 | FIS Requested | 06/18/2029 | 1 |