ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection · Anderson County

Tap 138kV 3325 Blackburn Switch – 3272 Palestine

2 active projects totalling 201 MW are queued to connect at Tap 138kV 3325 Blackburn Switch – 3272 Palestine in Anderson County, Texas, according to ERCOT's October 2026 report.

Active capacity
201 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0439Lumen Farm Solar SLFSolar201FIS Requested09/30/20280
24INR0450Lumen Farm BESS SLFBESS0FIS Requested09/30/20280