32INR0003 · Gas · Anderson County
Mule Deer Run Gas
Mule Deer Run Gas is a 1,263 MW natural gas project in Anderson County, Texas, connecting at #3308 Pin Oak 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2031.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 32INR0003
- Capacity
- 1,263 MW
- Fuel
- Gas (CC)
- Substation
- #3308 Pin Oak 345KV
- County
- Anderson County
- Interconnecting entity
- Anderson Energy Center, LLC
- Projected COD
- 07/01/2031
- Entered queue
- 11/06/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/06/2025Entered the queue with 1,263 MW, projected COD 07/01/2031
- 11/06/2025Screening → FIS Requested
Other projects at this substation
| Mule Deer Run Gas II | Gas | 1,263 MW | FIS Requested |
| Mule Deer Run Gas III | Gas | 1,263 MW | FIS Requested |