30INR0140 · BESS · Montague County
Enfinity Primrose
Enfinity Primrose is a 200 MW battery storage project in Montague County, Texas, connecting at (741) DYEMOUND Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/17/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0140
- Capacity
- 200 MW
- Fuel
- BESS (BA)
- Substation
- (741) DYEMOUND Substation 138kV
- County
- Montague County
- Interconnecting entity
- EG Primrose LLC
- Projected COD
- 07/17/2030
- Entered queue
- 07/14/2026
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/14/2026Entered the queue with 200 MW, projected COD 07/17/2030
- 07/14/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.