30INR0054 · Gas · Caldwell County

SCHNEIDER COMBINED CYCLE

COD delayed 1×

SCHNEIDER COMBINED CYCLE is a 880 MW natural gas project in Caldwell County, Texas, connecting at Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/10/2033. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0054
Capacity
880 MW
Fuel
Gas (CC)
Interconnecting entity
LCRA
Projected COD
05/10/2033
Entered queue
07/25/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 04/13/2032 → 05/10/2033 (+13 months)
  • 12/19/2025
    FIS Requested → IA Signed
  • 07/25/2025
    Entered the queue with 880 MW, projected COD 04/13/2032
  • 07/25/2025
    Screening → FIS Requested

Other projects at this substation

SCHNEIDER GAS RICEGas113 MWIA Signed
SCHNEIDER GAS RICE PHASE 2Gas113 MWIA Signed