29INR0222 · BESS · Coleman County

Paintbrush BESS1

Paintbrush BESS1 is a 201 MW battery storage project in Coleman County, Texas, connecting at Tap 345kV 1444 Brown Switch – 60040 Bluff Creek Switch & 1444 Brown Switch – 11406 Central Bluff Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0222
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Renew Development HoldCo LLC
Projected COD
10/15/2030
Entered queue
12/10/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/10/2025
    Entered the queue with 201 MW, projected COD 10/15/2030
  • 12/10/2025
    Screening → FIS Requested

Other projects at this substation

Paintbrush PV1Solar252 MWFIS Requested
Paintbrush PV2Solar252 MWFIS Requested
Paintbrush PV3Solar252 MWFIS Requested
Paintbrush PV4Solar252 MWFIS Requested