29INR0196 · Solar · Ellis County

Two Step Solar

Two Step Solar is a 402 MW solar project in Ellis County, Texas, connecting at Tap 345kV 1907 Venus - 68091 Navarro. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/17/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0196
Capacity
402 MW
Fuel
Solar (PV)
Interconnecting entity
Two Step Solar, LLC
Projected COD
09/17/2029
Entered queue
11/12/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/12/2025
    Entered the queue with 402 MW, projected COD 09/17/2029
  • 11/12/2025
    Screening → FIS Requested