29INR0167 · Gas · Caldwell County

Big Watt Power Austin-1

COD delayed 1×

Big Watt Power Austin-1 is a 449 MW natural gas project in Caldwell County, Texas, connecting at Tapping the 345 kV Double circuit Line: Zorn (Bus# 7042) - Lytton Springs (Bus# 9074) and Zorn (Bus# 7042) - Austrop (Bus# 7040).. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/15/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0167
Capacity
449 MW
Fuel
Gas (CC)
Interconnecting entity
Big Watt Power Austin-1 LLC
Projected COD
11/15/2028
Entered queue
09/26/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 11/01/2028 → 11/15/2028 (0 months)
  • 09/26/2025
    Entered the queue with 449 MW, projected COD 11/01/2028
  • 09/26/2025
    Screening → FIS Requested