29INR0108 · BESS · Dimmit County
7L Storage SLF
7L Storage SLF is a 0 MW battery storage project in Dimmit County, Texas, connecting at Tap 69kV 5870 Brundage - 5868 Big Wells. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/13/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0108
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- Tap 69kV 5870 Brundage - 5868 Big Wells
- County
- Dimmit County
- Interconnecting entity
- 7L Solar, LLC
- Projected COD
- 11/13/2029
- Entered queue
- 09/12/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/12/2025Entered the queue with 0 MW, projected COD 11/13/2029
- 09/12/2025Screening → FIS Requested
Other projects at this substation
| 7L Solar SLF | Solar | 72 MW | FIS Requested |