29INR0106 · BESS · San Patricio County
Kalina Storage
Kalina Storage is a 105 MW battery storage project in San Patricio County, Texas, connecting at 8606 Goddard 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0106
- Capacity
- 105 MW
- Fuel
- BESS (BA)
- Substation
- 8606 Goddard 345kV
- County
- San Patricio County
- Interconnecting entity
- Aurora Solar LLC
- Projected COD
- 12/01/2029
- Entered queue
- 04/21/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/15/2026Screening → FIS Requested
- 04/21/2025Entered the queue with 105 MW, projected COD 12/01/2029
Other projects at this substation
| Kalina Solar | Solar | 120 MW | FIS Requested |
| Bayou Creek Solar | Solar | 257 MW | IA Signed |
| San Patricio Energy Center BESS | BESS | 301 MW | FIS Requested |