29INR0084 · BESS · Young County

Jolly Rock Storage Center

Jolly Rock Storage Center is a 209 MW battery storage project in Young County, Texas, connecting at Tap 138kV 1431 GRAHAM Plant Switch - 11525 Short Grass Circuit 1.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/16/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0084
Capacity
209 MW
Fuel
BESS (BA)
Interconnecting entity
Jolly Rock Storage Center LLC
Projected COD
05/16/2029
Entered queue
12/19/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/23/2025
    Screening → FIS Requested
  • 12/19/2024
    Entered the queue with 209 MW, projected COD 05/16/2029

Other projects at this substation

No other projects at this substation.