28INR0498 · BESS · Hale County
Old Aqueduct BESS II
Old Aqueduct BESS II is a 301 MW battery storage project in Hale County, Texas, connecting at 23920 BLKWTRDR_5 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0498
- Capacity
- 301 MW
- Fuel
- BESS (BA)
- Substation
- 23920 BLKWTRDR_5 345kV
- County
- Hale County
- Interconnecting entity
- Tempus Power Management LLC
- Projected COD
- 03/01/2030
- Entered queue
- 03/05/2026
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/05/2026Entered the queue with 301 MW, projected COD 03/01/2030
- 03/05/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.