28INR0497 · Gas · Duval County

Cielo Vista Power II

COD delayed 1×

Cielo Vista Power II is a 350 MW natural gas project in Duval County, Texas, connecting at TAP 345 kV BUS # 5901 MIGUEL5 - BUS #80280. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/30/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0497
Capacity
350 MW
Fuel
Gas (IC)
Interconnecting entity
Cielo Vista Power II, LLC
Projected COD
03/30/2029
Entered queue
07/01/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/29/2028 → 03/30/2029 (+3 months)
  • 07/01/2026
    Entered the queue with 350 MW, projected COD 12/29/2028
  • 07/01/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.