LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0490 · BESS · Galveston County

Vertus Energy Storage 2

Vertus Energy Storage 2 is a 205 MW battery storage project in Galveston County, Texas, connecting at 38830 TNMAINLAND1 138 KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0490
Capacity
205 MW
Fuel
BESS (BA)
Interconnecting entity
Vertus Energy Storage 2 LLC
Projected COD
02/15/2028
Entered queue
01/21/2026
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/21/2026
    Entered the queue with 205 MW, projected COD 02/15/2028
  • 01/21/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.