28INR0403 · BESS · Cameron County
Ouroboros Grid BESS 3
Ouroboros Grid BESS 3 is a 201 MW battery storage project in Cameron County, Texas, connecting at 88337 Chalybe 345 kV. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0403
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 88337 Chalybe 345 kV
- County
- Cameron County
- Interconnecting entity
- Ouroboros Grid BESS Unit 3
- Projected COD
- 06/01/2028
- Entered queue
- 07/29/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/29/2025Entered the queue with 201 MW, projected COD 06/01/2028
Other projects at this substation