28INR0378 · BESS · Wichita County
Wichita Creek Storage
COD delayed 1×
Wichita Creek Storage is a 300 MW battery storage project in Wichita County, Texas, connecting at Tap 345 kV 6111 RILEY - 1730 KRUM WEST Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/15/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0378
- Capacity
- 300 MW
- Fuel
- BESS (BA)
- County
- Wichita County
- Interconnecting entity
- Wichita Solar II, LLC
- Projected COD
- 04/15/2030
- Entered queue
- 08/13/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/04/2028 → 04/15/2030 (+18 months)
- 08/13/2026Entered the queue with 300 MW, projected COD 10/04/2028
- 08/13/2026Screening → FIS Requested
Other projects at this substation