28INR0358 · Solar · Concho County
Cherry Sage Solar 1 SLF
Cherry Sage Solar 1 SLF is a 142 MW solar project in Concho County, Texas, connecting at (#60423) TREADWELL 138kV.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/23/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0358
- Capacity
- 142 MW
- Fuel
- Solar (PV)
- Substation
- (#60423) TREADWELL 138kV.
- County
- Concho County
- Interconnecting entity
- Cherry Sage Solar 1 LLC
- Projected COD
- 02/23/2029
- Entered queue
- 04/22/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/22/2025Entered the queue with 142 MW, projected COD 02/23/2029
- 04/22/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.