Barkley Creek Solar is a 312 MW solar project in Lampasas County, Texas, connecting at Tap 345 kV Line from Russel Gap Switch (Bus# 3348) - Killeen Switch (Bus# 3422). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0324
Capacity
312 MW
Fuel
Solar (PV)
Interconnecting entity
174 Power Global Properties, LLC
Projected COD
10/15/2029
Entered queue
08/19/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/19/2025
    Entered the queue with 312 MW, projected COD 10/15/2029
  • 08/19/2025
    Screening → FIS Requested