LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0305 · Solar · San Patricio County

Iron Cowboy Solar

COD delayed 1×

Iron Cowboy Solar is a 145 MW solar project in San Patricio County, Texas, connecting at Bus #8920 Haisley 4A 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/10/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0305
Capacity
145 MW
Fuel
Solar (PV)
Interconnecting entity
Vaquero II Solar LLC
Projected COD
07/10/2029
Entered queue
05/16/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/29/2028 → 07/10/2029 (+6 months)
  • 08/10/2026
    FIS Requested → IA Signed
  • 05/16/2025
    Entered the queue with 145 MW, projected COD 12/29/2028
  • 05/16/2025
    Screening → FIS Requested

Other projects at this substation

Iron Cowboy StorageBESS63 MWIA Signed