28INR0303 · Solar · Goliad County
Kuy Creek Solar 1 SLF
Kuy Creek Solar 1 SLF is a 235 MW solar project in Goliad County, Texas, connecting at Tap Coleto Creek (Bus # 8162) - Victoria (Bus# 8172) 138 kV CKT 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/20/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0303
- Capacity
- 235 MW
- Fuel
- Solar (PV)
- County
- Goliad County
- Interconnecting entity
- Kuy Creek Solar 1 LLC
- Projected COD
- 03/20/2029
- Entered queue
- 03/03/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/03/2025Entered the queue with 235 MW, projected COD 03/20/2029
- 03/03/2025Screening → FIS Requested
Other projects at this substation
| Kuy Creek Storage 1 SLF | BESS | 152 MW | FIS Requested |