28INR0290 · BESS · Erath County
Field Marshal Storage
Field Marshal Storage is a 151 MW battery storage project in Erath County, Texas, connecting at Dublin (1636) - Fullhouse (1652) 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/07/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0290
- Capacity
- 151 MW
- Fuel
- BESS (BA)
- Substation
- Dublin (1636) - Fullhouse (1652) 138kV
- County
- Erath County
- Interconnecting entity
- Field Marshal Storage LLC
- Projected COD
- 05/07/2029
- Entered queue
- 03/20/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/20/2025Entered the queue with 151 MW, projected COD 05/07/2029
- 03/20/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.