LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0286 · Wind · Fannin County

2 Cedar Wind

2 Cedar Wind is a 180 MW wind project in Fannin County, Texas, connecting at Tap 345kV 1729 Valley South – Anna Switch 2373. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/02/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0286
Capacity
180 MW
Fuel
Wind (WT)
Interconnecting entity
SunWR, LLC
Projected COD
05/02/2028
Entered queue
07/07/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/26/2026
    Screening → FIS Requested
  • 07/07/2025
    Entered the queue with 180 MW, projected COD 05/02/2028

Other projects at this substation

No other projects at this substation.