28INR0267 · Solar · Cottle County
Soluce Cotton Solar
Soluce Cotton Solar is a 203 MW solar project in Cottle County, Texas, connecting at Tap 345kV 59904 COTTONWOOD - 60500 EDITH CLARKE. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 08/13/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0267
- Capacity
- 203 MW
- Fuel
- Solar (PV)
- County
- Cottle County
- Interconnecting entity
- CTPB1, LLC
- Projected COD
- 08/13/2029
- Entered queue
- 02/14/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/14/2025Entered the queue with 203 MW, projected COD 08/13/2029
Other projects at this substation
| Soluce Cotton Storage | BESS | 202 MW | Screening |